RECORDS AND REPORTS
Detailed daily reports shall be prepared for each inspection and test by the Special Inspector and
Testing Laboratory.
Reports shall include:
Date of test or inspection
Name of Inspector or Technician
Location of specific areas tested or inspected
Description of test or inspection and results
Applicable ASTM standard
Weather conditions
Inspector signature
Any discrepancies from the Contract Documents found during a Special Inspection shall be immediately reported to the Contractor. If the discrepancies are not corrected, the Special
Inspector shall notify the Contractor QC Manager. Reports shall document all discrepancies identified and the corrective action taken.
At the completion of the work requiring Special Inspections, the Special Inspector shall provide a statement to the Contractor and Designer of Record that all work was